Question: project has an initial cost of $50,000. The incremental inflows associated
Please show all work and do not use excel since that is not the way I need to learn the material.
A project has an initial cost of $50,000. The incremental inflows associated with the project are $20,000 in year one, $15,000 in years two and three, and $10,000 in year four. The appropriate discount rate for this project is 11%.
- What is the project’s NPV?